Project Status

29th October 2019

Tower 1A

  1. Terrace lighting arrest work completed. 

  2. Terrace ring mainline work completed. 

  3. Terrace ducts and shafts civil work completed (except top covering)

  4. Basement lobby blockwork and plastering work completed. 

  5. Staircase railings fixing works completed (Both staircase) 

  6. Door frames fixing work completed 

  7. Window Grills fixing work completed 

  8. Tiling work up to 12th floor completed (balance under progress) 

  9. Flats internal electrical & plumbing work up to 11th floor completed, 12 & 13th under progress  

  10. Corridor electrical work completed (except stilt floor) 

  11. Toilets false ceiling works 8th floor completed, above floors under progress 

  12. Internal painting work like primer & putty work ground to 11th floor under progress

  13. External one coat colour yet to start. 

  14. UPVC windows fixing works overall 90% completed

  15. Internal joinery works up to 11th floor completed. Above floors under progress

  16. Lift front granite cladding works up to 10th floor completed. Balance under progress

  17. Staircase & Corridor tiling works completed 

  18. Lift installation works under progress 

​

Tower 1 B

  1. Terrace waterproofing works completed

  2. All sides plastering works completed. 

  3. Block works completed (except basement and electrical rooms)

  4. Internal plastering 100% completed

  5. Terrace OHT waterproofing & plastering work completed

  6. Door frame fixing up to 9th floor completed. Above floors under progress

  7. Window grill fixing up to 7th floor completed (Balance after UPVC windows fixing)

  8. Internal tiling works up to 7th floor completed, 8th & 9th floor under progress

  9. Internal plumbing work completed 

  10. Internal electrical chiselling works completed. Wire pulling up to 3rd floor completed

  11. Terrace ring mail line works completed 

  12. Lift front door frame fixing work under progress

  13. Terrace ducts and shafts civil work completed (except top covering) 

 

Tower 2A & 2B

  1. Flats hand over work under progress (clients)   

  2. In all flats snagging work under progress (clients checklist for hand over) 

  3. In all flats plumbing fixtures fixing work completed

  4. In the corridor and staircase housekeeping work under progress

  5. In all floors maintenance work under progress

   

Basement works

  1. Lower & Upper Exit Ramp flooring concrete and finishing work completed. 

  2. Lower & Upper Entry Ramp flooring concrete and finishing work yet to start. 

  3. Upper & Upper basement Gas cutting work completed (all sides RCC wall studs & Columns) 

  4. Upper basement screed concrete completed

  5. Fire fighting pipeline fixing work completed

  6. From 1A podium to 2A Upper basement entry RCC work completed (Ready to access directly to upper basement) 

  7. 2 A & 2B Upper basement housekeeping work under progress

​

External works (Hardscape & Softscape)

  1. Northside compound with drainwork completed up to 1A Tower Entrance of the podium 

  2. Southside compound with Drainwork completed up to 1A Tower Entrance of the podium 

  3. Eastside compound with feature elevation work completed 

  4. Northside Courtyard work completed in 2A & 2B towers (Southside under progress)

  5. Electrical poles fixing works completed 

  6. STP RCC walls concrete work completed, STP above ramp works RCC works completed

  7. Front compound plastering work under progress. 

  8. Front Gate Structure works completed. Finishing works under progress

  9. Security cabin structure and plastering work completed

  10. Pathway pavers in 2A & 2B tower north side completed, south side under progress

30th September 2019

Tower 1A​

  1. Terrace ring mail line work completed

  2. Terrace ducts and shafts civil work completed except top covering 

  3. Basement lobby block work and plastering work completed

  4. Staircase railing work completed (both staircase)

  5. Door frame fixing work completed

  6. Window grills fixing work completed

  7. Tiling work up to 12th floor completed. Balance under progress

  8. Flats internal electrical & plumbing work up to 11th floor completed, 12th & 13th floor under progress 

  9. Corridor electrical work completed except stilt floor

  10. Toilets false ceiling works 8th floor completed, above floors under progress

  11. Internal painting works like primer and putty work ground to 11th floor under progress

  12. External one coat colour yet to start

  13. UPVC window fixing work overall 90% completed

  14. Internal joinery work up to 11th floor completed. Above floors under progress

  15. Lift front granite cladding work up to 10th floor completed. Balance under progress

  16. Staircase & corridor tiling work completed

  17. Lift installation work under progress

​

Tower 1 B

  1. Terrace waterproofing work completed

  2. All sides plastering work completed

  3. Block work completed except basement and electrical rooms

  4. Internal plastering 100 % completed

  5. Terrace OHT water proofing and plastering work completed

  6. Door frame fixing up to 9th floor completed. Above floors under progress

  7. Window grill fixing up to 7th floor completed. Balance after UPVC window fixing

  8. Internal tiling work up to 7th floor completed, 8th and 9th floor under progress

  9. Internal plumbing work completed

  10. Internal electrical chiseling work completed. Wire pulling up to 3rd floor completed

  11. Terrace ring mail line work completed

  12. Lift front door frame fixing work under progress

  13. Terrace ducts and shafts civil works completed except top covering 

​

Basement works

  1. Lower and upper exit ramp flooring concrete and finishing work completed

  2. Lower and upper entry ramp flooring concrete and finishing work yet to start

  3. Upper basement Gas cutting work completed (all sides RCC wall studs & columns)

  4. Upper basement screed concrete completed 

  5. Fire fighting pipe line fixing work completed

  6. From 1A podium to 2A upper basement entry RCC work completed (ready to access directly to upper basement)

  7. 2A and 2B upper basement house keeping work under progress

 

External work (Hardscape and Softscape)

  1. North and south side compound with drain work completed up to Tower 1A entrance of the podium

  2. East side compound with feature elevation work completed

  3. North side courtyard work completed in 2A and 2B towers. South side under progress

  4. Electrical pole fixing work completed

  5. STP RCC walls concrete work completed, STP above ramp work RCC work completed

  6. Front compound plastering work under progress

  7. Front gate structure work completed. Finishing work under progress

  8. Security cabin structure and plastering work completed

  9. Pathway pavers in Tower 2A and 2B north side completed, south side under progress

28th August 2019

Tower 1 A

  1. Lift frame fixing works under progress

  2. Corridor tiles from first to fourth floor under progress

  3. Corridor hand railing works under progress

  4. Basement lobby plastering under progress

  5. Staircase hand railings fixing work ground to penthouse completed

  6. Door frame fixing in penthouses under progress

  7. Window grills above 11th floor under progress

  8. Tiling work 12th floor & penthouses under progress

  9. Internal Toilet electrical wires pulling up to 8th completed, above 9th floor under progress

  10. Toilet false ceiling work stared. Fourth floor under progress.

  11. Internal painting work, primer & putty up to 9th floor completed, balance under progress

  12. Corridors up to 5th floor primer & putty work completed. External primer work completed

  13. UPVC window fixing work overall 90% completed (Balcony french windows from 8th to penthouse pending)

  14. Internal joinery work up to 10th floor completed. Above floors under progress

  15. Internal flat plumbing work completed. Duct & balcony lines under progress

  16. Terrece ring main lines under progress. OHT lines under progress

​

Tower 1B

  1. Terrace waterproofing work 100 % completed

  2. All sides plastering work completed (except OTS areas)

  3. North side OTS plastering completed, south side under progress

  4. Block work ground to terrace 100% completed (Basement lobby area under progress)

  5. Internal rough plastering 100 % completed (toilet and kitchen area)

  6. Internal plastering up to 8th floor completed (9th & 10th under progress)

  7. Door frame fixing above 8th floor under progress

  8. Window grill fixing up to 7th floor completed. Balance under progress

  9. Internal tiling work up to 5th floor completed, 6th floor under progress

  10. Internal plumbing works completed. Duct lines under progress

  11. Internal electrical work chiselling and conduit fixing work completed

  12. Electrical wire pulling work in 2nd floor under progress

  13. Lift shaft scaffolding under progress

​

Tower 2A & 2B

  1. Flats handing over work under progress

  2. In all flats snagging work under progress

  3. In all flats plumbing fixture fixing work completed

  4. In the corridor and staircase house keeping works under progress

  5. In all floors maintaince works under progress

​

External work (Hardscape & Softscape)

  1. North side compound with drain work completed up to Tower 2A entrance of the podium

  2. South side compound with drain work completed up to Tower 2A entrance of the podium

  3. East side compound with feature elavation works completed

  4. North side courtyard work completed in Towers 2A&2B. South side under progress

  5. Electrical poles fixing work completed

  6. STP RCC walls concrete work completed.

  7. Front compound plastering work under progress

  8. Front gate structure work completed. Finishing work under progress

  9. Security cabin structure and plastering work completed

  10. Pathway pavers in Tower 2A&2B north side completed, south side under progress

25th July 2019

Tower 1 A

  1. Terrace water proofing works completed

  2. Upper terrace OHT internal waterproofing and testing completed

  3. Upper terrace plastering works completed

  4. Basement lobby block work under progress

  5. Staircase railing fitting work up to 8th floor completed (Common staircase)

  6. Door frame fixing up to 11th floor completed, 12th floor under progress

  7. Window grills above 8th floor under progress

  8. Tiling work 10th floor under progress

  9. Internal toilet electrical wires pulling up to 7th floor completed, above 8th floor under progress

  10. Basement grade slab concrete works completed, ramp works under progress

  11. Toilet false ceiling works stared. Fourth floor under progress

  12. Internal painting work like primer & putty work ground to 8th floor under progress

  13. External primer works completed

  14. UPVC window fixing work overall 90% completed

  15. Internal joinery work up to 10th floor completed. Above floors under progress

  16. Lift front wall block work completed. Lift installation basic work started

  17. Staircase & corridor tiling work started (from ground to terrace floor) up to 7th floor completed

  18. Internal water proofing works completed

​

Tower 1B

  1. Terrace waterproofing work 50% completed

  2. East and south plastering work under progress (50% completed)

  3. North side 8th floor to terrace plastering work completed

  4. Block work completed except for parapet walls (Basement yet to start)

  5. Internal plastering 100% completed

  6. Internal water proofing works completed

  7. Door frame fixing up to 7th floor completed. Above floors under progress.

  8. Window grill fixing up to 7th floor completed. Balance under progress

  9. Internal tiling works up to 5th floor completed, 6th floor under progress

  10. Internal plumbing works 12th & 13th floor under progress

  11. Internal elecrtical works 12th & 13th floor under progress

  12. Lift front wall block work floor completed

  13. Lift shaft work under progress

  14. Electrical & Plumbing work 10th & 11th floor under progress

 

Tower 2A & 2B

  1. Flats handing over work under progress  

  2. All flats snagging work under progress (Clients check list for hand over)

  3. All flats plumbing fixtures fixing works completed

  4. In the corridor and staircase house keeping works under progress

  5. All floors maintenance work under progress

​

External Work (Hardscape & Softscape)

  1. North side compound with drain work completed up to Tower 2A Entrance of the podium 

  2. South side compound with drain work completed up to Tower 2A Entrance of the podium

  3. East side compound with feature elevation works completed

  4. North side courtyard work completed in 2A & 2B Towers. South side under progress

  5. Electrical poles fixing work completed

  6. STP RCC walls concrete work completed, STP above ramp works RCC works completed

  7. Front compound plastering work under progress

  8. Front gate structure works completed. Finishing works under progress

  9. Security cabin structure and plastering work completed

  10. Pathway pavers in 2A & 2B tower north side completed, south side under progress

30th June 2019

Tower 1A

  1. Terrace water proofing work under progress

  2. Upper terrace OHT internal waterproofing work completed. Testing under progress

  3. All three sides up to terrace  plastering work completed 

  4. Upper terrace block work completed

  5. Block work in basement under progress

  6. Staircase railing work under progress 

  7. Door frame fixing up to 10th floor completed, 11th floor under progress

  8. Window grill fixing up to 7th floor completed, above 8th floor under progress

  9. Internal plastering completed 

  10. Tiling work up to 9th floor completed. 10th floor under progress

  11. Internal toilet plumbing lines completed 

  12. Internal toilet electrical chiseling lines & conduit fixing completed

  13. Internal toilet electrical wires pulling up to 7th floor completed, above 8th floor under progress 

  14. Basement grade slab concrete work completed, ramp work under progress

  15. Toilet false ceiling work stared, ground and first floor under progress

  16. Internal painting work like primer and putty works ground to 7th floor under progress

  17. External primer works completed

  18. UPVC windows fixing works overall 80% completed

  19. Internal joinery works up to 8th floor completed. Above floors under progress

  20. Lift front wall block work completed. Lift installation basic works started

  21. Staircase and corridor tiling work started (from penthouse to ground floor)

  22. Internal water proofing work completed

​

Tower 1B

  1. All RCC concrete work completed

  2. Terrace waterproofing work started

  3. North side 8th floor to terrace plastering work under progress.

  4. Block works completed except parapet wall (25% completed)

  5. Internal plastering penthouses under progress

  6. Internal water proofing work in penthouse under progress

  7. Door frame fixing up to 7th floor completed. Above floors under progress

  8. Window grill fixing up to 7th floor completed. Balance under progress

  9. Internal tiling works up to 3rd floor completed, 4th & 5th floor under progress

  10. Internal plumbing work 12th & 13th floor under progress

  11. Internal electrical work 12th & 13th floor under progress

  12. Lift front wall block work up to 9th floor completed. Balance under progress

  13. Lift shaft works under progress

  14. Electrical & plumbing work 10th and 11th floor under progress

​

Tower 2A and 2B

  1. Flats handing over work under progress (clients)  

  2. All flats snagging work under progress (clients check list for hand over)

  3. All flats plumbing fixtures fixing work completed

  4. Corridor and staircase house keeping works under progress

  5. All floors maintaince works under progress

 

Basement works

  1. Lower and upper exit ramp flooring concrete and finishing work completed

  2. Lower and upper entry ramp flooring concrete and finishing work yet to start

  3. Lower and upper basement gas cutting work completed (all sides RCC wall studs and columns)

  4. Upper basement screed concrete completed

  5. Fire fighting pipe line fixing work completed

  6. From 1A podium to 2A upper basement entry RCC work completed (ready to access directly to upper basement)

  7. 2A and 2B upper basement house keeping work under progress

 

External works (Hardscape & Softscape)

  1. North side compound with drain work completed up to 2A tower entrance of the podium 

  2. South side compound with drain work completed up to 2A tower entrance of the podium

  3. East side compound with feature elavation works completed

  4. North side courtyard works completed in 2A and 2B. South side under progress

  5. Electrical poles fixing work completed

  6. STP RCC walls concrete work completed, STP above ramp works RCC works completed

  7. Front compound plastering work under progress

  8. Front gate structure work completed. Finishing work under progress

  9. Security cabin structure and plastering work completed

  10. Pathway pavers in 2A and 2B north side completed, south side under progress

27th May 2019

Tower 1A

  1. Upper terrace all concrete works completed.

  2. Upper terrace OHT internal water proofing works under progress.

  3. West side 8th floor to terrace floor plastering work completed. 

  4. Block work lift and basement under progress.

  5. Balcony Railings fixing work 95% completed, balance under progress.

  6. Door frame fixing up to 8th floor completed, 9th floor under progress.

  7. Window Grill fixing upto to 4th to 7th floor completed, 8th and 9th floor under progress.

  8. Internal plastering upto 8th floor completed, 9th floor marking under progress. 

  9. Tiling work upto 7th floor completed, 8th and 9th floor under progress.

  10. Internal toilet plumbing line up to 12th floor completed, balance under progress. 

  11. Internal toilet electrical chiseling lines & conduit fixing up to 12th floor completed, balance under progress. 

  12. Internal toilet electrical wires pulling up to 5th floor completed, balance under progress.

  13. Podium work concrete 100% completed, Ramp side wall work under progress.

  14. Water proofing works 11 and penthouses under progress. Terrace brick bat work under progress.

 

Tower 1B

  1. Terrace slab de-shuttering work under progress.

  2. Above terrace head rooms columns concrete work completed.

  3. Elevation pergola RCC works completed. 

  4. Terrace parapet upstanding beams completed.

  5. Block work 11th floor 3 flats completed, under progress (penthouses block work under progress).

  6. External plastering 4th floor to 8th floor completed.

  7. Door frame fixing up to 5th floor completed (6 & 7th floor under progress).

  8. Window grill fixing up to to 6th floor completed (Balance under progress).

  9. Internal plastering 5th & 6th floor under progress.

  10. Internal plumbing work upto 9th & 10th floor under progress.

  11. Internal electrical work up to 9th & 10th floor under progress.

  12. Water proofing works up to 9th floor completed, 10th under progress.

  13. Podium ramp RCC works completed.

  14. Balcony railings fixing work 4th to 8th floor under progress.

 

Basement Works

  1. Lower and upper exit ramp flooring concrete and finishing work completed.

  2. Lower and upper entry ramp flooring concrete and finishing work yet to start.

  3. Upper and upper basement gas cutting work completed (all sides RCC wall studs and columns).

  4. Upper basement screed concrete completed. 

  5. Fire fighting pipe line fixing work completed.

  6. From 1A podium to 2A upper basement entry RCC work completed (Ready to access directly to upper basement).

  7. 2A and 2B Upper basement housekeeping works under progress.

29th april 2019

Tower 1A

  1. Upper terrace works like SHR, LHR, Pergolas, and elevation pillars concrete work completed.

  2. Upper terrace OHT top slab completed.

  3. West side 8th floor to terrace floor  plastering work completed. 

  4. North side 8th to terrace plastering completed.

  5. Block work parapet walls completed, lift and staircase head rooms under progress.

  6. Balcony railings fixing work all floors completed, except hoist running area.

  7. Door frame fixing up to 7th floor completed, 8th floor under progress.

  8. Window grill fixing 4th to 7th floor completed.

  9. Internal plastering up to 7th floor completed, 8th floor marking under progress. 

  10. Tiling work up to 7th floor completed.

  11. Internal toilet plumbing line up to 12th floor completed, balance under progress. 

  12. Internal toilet electrical chiseling lines & conduit fixing up to 12th floor completed, balance under progress. 

  13. Internal toilet electrical wires pulling up to 3rd floor completed, balance under progress. 

  14. Podium work concrete up to 85% completed, balance under progress.

  15. Water proofing works up to 10th floor completed, 11th floor and penthouses under progress.

​

Tower 1B

  1. Terrace slab concrete work completed.

  2. Above terrace OHT & head rooms columns concrete work under progress.

  3. Elevation pergola column shuttering work under progress. 

  4. Terrace parapet upstanding beams under progress.

  5. Block work 10th floor completed, 11th floor under progress.

  6. External plastering 4th floor to 8th floor completed.

  7. Door frame fixing up to 5th floor completed. 6th & 7th floor under progress.

  8. Window grill fixing up to 6th floor completed. Balance under progress.

  9. Internal plastering up to 4th floor completed, 5th & 6th floor button mark under progress.

  10. Internal plumbing work up to 8th floor completed. 9th floor under progress.

  11. Internal electrical work up to 9th floor completed. 10th floor under progress.

  12. Water proofing works up to 8th floor completed, 9th floor under progress.

  13. Podium ramp excavation work completed. Foundation work under progress.

  14. Balcony railings fixing work 4th to 8th floor under progress.

​

Tower 2 A & 2B

  1. Flats handing over work under progress.

  2. All flats snagging work under progress.

  3. All flats plumbing fixtures fixing work under progress.

  4. Corridor and staircase house keeping works under progress.

  5. Penthouses wooden staircase work completed.

 

Basement works

  1. Lower & upper exit ramp flooring concrete and finishing work completed.

  2. Lower & upper entry ramp flooring concrete and finishing work yet to start.

  3. Upper & upper basement gas cutting work completed.

  4. Upper basement screed concrete completed. 

  5. Fire fighting pipe line fixing work completed.

  6. From 1A podium to 2A upper basement entry RCC work completed. 

  7. 2A & 2B Upper basement house keeping works under progress.

28th March 2019

Tower 1A

  1. Upper terrace works like SHR, LHR, Pergolas and elevation pillars concrete work completed.

  2. Upper terrace OHT side walls completed, top slab shuttering work under progress.

  3. West side 8th floor to terrace floor  plastering work completed. 

  4. North side scaffolding erection work completed, plastering under progress.

  5. Block work upper penthouse completed. Parapet walls near expansion joint under progress.

  6. Balcony railings fixing work 9th to penthouse under progress.

  7. Door frame fixing up to 7th floor under progress.

  8. Window grill fixing up 4th to 7th floor under progress.

  9. Internal plastering 5th and 6th floor completed. 7th floor under progress. 

  10. Tiling work 4th and 5th floor completed, 6th and 7th floor under progress.

  11. Internal toilet plumbing line up to 10th floor completed, 11th floor under progress. 

  12. Internal electrical works up to 11th floor completed, penthouses under progress.

  13. Podium work concrete up to 70% completed, balance under progress.

  14. Water proofing works up to 10th floor completed, 11th and penthouses under progress.

 

Tower 1B

  1. Upper penthouse floor concrete work completed.

  2. Upper penthouse to terrace slab, first three flats column concrete work completed.

  3. Upper penthouse to terrace slab, Balance three flats column concrete work under progress.

  4. Terrace slab first three flats shuttering work under progress.

  5. Block work in 9th floor completed. 10th floor under progress.

  6. External plastering 4th to 8th floor completed.

  7. Door frame fixing up to 4th floor completed. Further under progress.

  8. Window grill fixing up to 4th floor completed. Further under progress.

  9. Internal plastering up to 3rd floor completed. 4th floor under progress. 5th floor button mark under progress.

  10. Internal plumbing work up to 8th floor completed. 9th floor under progress.

  11. Internal electrical work up to 9th floor completed. 10th floor under progress.

  12. Water proofing works up to 8th floor completed, 9th under progress.

  13. Podium ramp excavation work completed. Foundation work under progress.

  14. Balcony railings fixing work 4th to 8th floor under progress.

 

Tower 2A

  1. Flats handing over work under progress.  

  2. In all flats snagging work under progress.

  3. In all flats plumbing fixtures fixing work under progress.

  4. In the corridor and staircase house keeping works under progress.

  5. Penthouses wooden staircase posing work completed.

 

Basement works

  1. Lower & Upper exit ramp flooring concrete and finishing work completed.

  2. Lower & Upper Entry Ramp flooring concrete and finishing work yet to start.

  3. Upper & Upper basement gas cutting work completed (all sides RCC wall studs & Columns).

  4. Upper basement Screed concrete completed. 

  5. Fire fighting pipe line fixing work completed.

  6. From 1A podium to 2A upper basement entry RCC work completed (Ready to access next week).

  7. Columns & ceiling touchup works completed.

20th February 2019

Tower 1 A

  1. Upper terrace works like SHR, LHR, Pergolas, and elevation pillars concrete work completed.

  2. Upper terrace OHT side walls shuttering work under progress.

  3. 8th floor to terrace floor west side scaffolding completed, plastering under progress.

  4. Block work upper penthouse and terrace parapet walls under progress.

  5. Balcony railings fixing work 9th to penthouse under progress.

  6. Door frame fixing up to 7th floor under progress.

  7. Window grill fixing up 4th to 7th floor under progress.

  8. Internal plastering 5th & 6th floor under progress. 7th floor button mark under progress.

  9. Tiling work 4th floor under progress.

​

Tower 1 B

  1. Lower penthouse floor concrete work completed.

  2. Lower to upper penthouse first three flats column concrete work completed.

  3. Block work in 9th floor under progress. 

  4. External plastering 4th to 8th floor under progress (80% completed). Balance under progress.

  5. Door frame fixing up to 3rd floor completed.

  6. Window grill fixing up to 3rd floor completed.

  7. Internal plastering 1st to 3rd floor under progress. Balance floors button mark under progress.

​

Tower 2 A & 2B

  1. Lobby flooring granite work completed.

  2. Lobby false ceiling with wiring work completed.

  3. Lobby putty work under progress.

  4. Lobby joinery work completed (hardware fittings pending).

  5. Lobby front steps flooring granite work under progress.

  6. In all flats snagging work under progress (clients check list for hand over).

  7. In all flats fixtures fixing work under progress (85% completed).

  8. Penthouses staircase wooden threads polish work under progress.

​

Basement

  1. Lower basement chamber cleaning & finishing work completed.

  2. Lower basement ceiling electrical checking works completed.

  3. Upper basement gas cutting work under progress (all sides RCC wall studs & Columns).

  4. Upper basement screed concrete under progress (60% completed).

  5. Fire fighting pipe line fixing work completed.

  6. Columns & ceiling touchup works under progress.

24th January 2019

Tower 1 A

  1. Upper terrace works like SHR, LHR, Pergolas and elevation pillars concrete work completed.

  2. Upper terrace OHT bottom slab shuttering work under progress.

  3. 8th floor to terrace floor scaffolding under progress.

  4. Block work lower penthouse and terrace parapet walls under progress.

  5. Balcony railings fixing work 9th to penthouse under progress.

  6. Door frame fixing up to 5th floor completed.

  7. Window grill fixing up to to 4th floor completed.

  8. Internal plastering 4th & 5th floor under progress. 6th floor button mark under progress.

  9. Tiling work 1st floor to 3rd floor under progress.

​

Tower 1 B

  1. 11th floor slab concrete work completed.

  2.  11th to 12th floor first three flats column concrete work completed. Shuttering work progress. 

  3. Block work in 8th floor completed, 9th marking course under progress.

  4. External plastering 4th floor to 8th floor under progress (80% completed). Balance under progress.

  5. Door frame fixing up to 3rd floor completed.

  6. Window grill fixing up to 3rd floor completed.

  7. Internal plastering 1st to 3rd floor under progress. Balance floors button mark under progress.

​

Tower 2 A & 2B

  1. Lobby flooring granite work completed.

  2. Lobby false ceiling with wiring work completed.

  3. Lobby putty work under progress.

  4. Lobby joinery work completed (hardware fittings pending)

  5. Lobby front steps flooring granite work completed.

  6. In all flats snagging work under progress (clients check list for hand over).

  7. In all flats fixtures fixing work under progress (75% completed).

  8. Penthouses staircase wooden threads polish work under progress.

​

Basement

  1. Lower basement chamber cleaning & finishing work completed.

  2. Lower basement ceiling electrical checking works completed.

  3. Upper & Upper basement gas cutting work under progress (all sides RCC wall studs & columns)

  4. Upper basement screed concrete under progress (60 % completed)

  5. Fire fighting pipe line fixing work completed.

  6. Columns & ceiling touchup works under progress.

27th December 2018

Tower 1 A

  1. Terrace Slab completed. 

  2. Upper terrace works like head rooms and pergola shuttering work under progress. 

  3. External plastering up to 8th floor completed. 8th floor to terrace floor scaffolding under progress. 

  4. Block work lower pent house under progress. 

  5. Balcony railings fixing work up to 8th floor completed. Balance under progress. 

  6. Internal plastering 1st to 3rd floor under progress. Balance floors button mark under progress. 

​

Tower 1 B

  1. 10th floor balance three flats concrete work completed. 

  2. 11th floor first three flats column concrete work under progress.  

  3. Block work in seventh floor completed, 8th floor under progress. 

  4. External plastering up to 4th floor completed. 4th floor to 8th floor under progress, 50% completed. 

  5. Internal plastering 1st to 3rd floor under progress. Balance floors button mark under progress. 

​

Tower 2 A

  1. Lobby flooring granite work completed. 

  2. Lobby false ceiling with wiring work completed. 

  3. Lobby putty work under progress. 

  4. Lobby joinery work completed (hardware fittings pending) 

  5. Lobby front steps flooring granite work under progress. 

  6. In all flats snagging work under progress.(Clients check list for hand over) 

  7. In all flats fixtures fixing work under progress, 50% completed. 

  8. Penthouses staircase wooden threads polish work under progress. 

​

Tower 2 B

  1. Lobby flooring granite work completed. 

  2. Lobby false ceiling with wiring work completed. 

  3. Lobby putty work under progress. 

  4. Lobby joinery work completed (Hardware fittings pending) 

  5. Lobby front steps flooring granite work under progress. 

  6. In all flats snagging work under progress. (Clients check list for hand over) 

  7. In all flats fixtures fixing work under progress, 50% completed. 

  8. Penthouses staircase wooden threads polish work under progress. 

1st October 2018

Tower  1A

  1. Lower penthouse floor first three flats concrete work completed.

  2. Lower penthouse floor balance three flats shuttering work under progress.

  3. External plastering upto 7th floor completed.

  4. Block work 9th floor under progress.

  5. Balcony railings fixing work under progress.

  6. Internal plastering 1st floor under progress. 2nd floors button mark under progress.

​

Tower 1B

  1. 8th floor first three flats concrete work completed.

  2. 8th floor balance three flats ready to pour concrete.

  3. Block work in 6th floor under progress.

  4. 1B fire fight driveway (east side podium) area concrete work completed.

  5. Balcony railings work under progress.

  6. External plastering up to 3rd floor under progress.

​

Tower 2A

  1. Corridor one coat colour under progress.

  2. Common and fire fighting staircase surrounding one colour under progress.

  3. Penthouses internal staircases wood work for thread under progress.

  4. Penthouses internal putty work under progress.

  5. Fire fighting doors and shaft doors fixing work under progress.

  6. External colour second coat 50% completed. Balance work under progress.

  7. All flats house keeping, acid wash and soap wash under progress.

​

Tower 2B

  1. Corridor one coat colour under progress.

  2. Common and fire fighting staircase surrounding one colour under progress.

  3. Penthouses internal staircases wood work for thread under progress.

  4. Penthouses internal putty work under progress.

  5. Fire fighting doors and shaft doors fixing work under progress.

  6. External colour second coat 50% completed.

  7. All flats house keeping, acid wash and soap wash under progress.

  8. Upto 5 floors internal colour completed.

20th September 2018

Tower 1A

  1. 11th floor balance three flats concrete work completed.

  2. 11th & 12 floor first three flats shuttering work under progress.

  3. External plastering up to 3rd floor completed. 4th floor to 7th floor under progress.

  4. Block work 8th floor under progress.

  5. Balcony railings fixing work under progress.

  6. Internal plastering 1st to 3rd floor under progress. Balance floors button mark under progress.

​

Tower 1B

  1. 8th floor first three flats concrete work completed.

  2. 8th floor balance three flats ready to pour concrete.

  3. Block work in 6th floor under progress.

  4. 1B fire fight driveway (east side Podium) area concrete work completed.​

​

Tower 2A

  1. Corridor one coat colour under progress.

  2. Common and fire fighting staircase surrounding one colour under progress.

  3. Pent houses internal staircases wood work for thread under progress.

  4. Pent houses internal putty work under progress.

  5. Fire fighting doors and shaft doors fixing work under progress.

  6. External colour second coat 50% completed. Balance work under progress.

  7. All flats house keeping, acid wash and soap wash under progress.

​

Tower 2B

  1. Corridor one coat colour under progress.

  2. Common and fire fighting staircase surrounding one colour under progress.

  3. Pent houses internal staircases wood work for Thread under progress.

  4. Pent houses internal putty work under progress.

  5. Fire fighting doors and shaft doors fixing work under progress.

  6. External colour second coat 50% completed.

  7. All flats house keeping, acid wash and soap wash under progress.

  8. Up to 5 floors internal colour completed.

28th August 2018

Tower 2A

  1. Corridor tiles laying upto penthouse floor completed.

  2. Common and fire fighting Staircase tiling up to terrace completed.

  3. Internal plastering of pent houses completed.

  4. All flats house keeping work completed. Acid wash and soap wash under progress.

​

Tower 2B

  1. Corridor tiles laying upto pent house completed.

  2. Common and fire fighting Staircase flooring upto terrace completed.

  3. Flats internal Tiles laying upto Pent houses 100% completed.

  4. External Glass work in progress.

​

Tower 1A 

  1. 11th floor completed.

  2. External plastering upto the 7th floor under progress.

​

Tower 1B

  1. 7th floor completed.

  2. 1B driveway area, UG Sump above ramp concrete work completed.

19th July 2018

Tower 1A

  1. 11th floor first three flats shuttering and bar bending work under progress.     

  2. 10th to 11th floor balance three flats columns concrete work under progress.    

  3. External plastering up to 3rd floor completed. 4th floor to 7th floor under progress.               

  4. Block work 8th floor under progress.        

  5. Marketing and site office finishing works under progress (Flat No 001 & 005).

         

Tower 1 B                    

  1. Sixth floor balance three flats concrete work completed.                

  2. Sixth floor to 7th floor first three flats column concrete work under progress.     

  3. Block work in fourth floor under progress. 1B driveway (Podium) area shuttering and barbending work copmleted.                

  4. 1B driveway (Podium) area (east side) Excavation and rock work under progress.                

 

Tower 2 A                    

  1. Corridor tiles laying up to 12th floor completed.                

  2. Common and fire fighting Staircase tiling up to 12th floor completed.                

  3. MS works in internal flats completed (Window Grills). Staircase railings completed. Pent houses individual staircase completed.              

  4. Internal plastering pent houses completed.     

  5. Flats internal Tiles laying up to Pent houses 100% completed.                

  6. External primer and colour applying one coat is over, second coat started.                

  7. All flats house keeping work completed. Acid wash and soap wash started.            

 

Tower 2 B                    

  1. Corridor tiles laying up to 12th floor completed.                

  2. Common and fire fighting Staircase tiling up to 12th floor completed.                

  3. Pent house tiling under progress.               

  4. MS works in internal flats under progress (Window Grills). Staircase railings completed.         

  5. Internal plastering pent houses completed except some touch up works.

  6. Flats internal Tiles laying upto 10th floor completed. Pent houses under progress. External plastering 100 % completed.               

  7. External primer and colour applying work under progress.                

7th June 2018

Tower 1A                    

  1. 10th floor First three flats concrete work competed.                

  2. 10th floor Balace three flats shuttering and bar-bending work completed, ready to pour concrete.                

  3. Block work Fifth and Sixth floor under progress.                

  4. External plastering started in North & North west corner (4 and 5 flats series).    

  5. Marketing and site office finishing works under progress (Flat No 001 & 005).                

Tower 1B                    

  1. Fifth floor Balance three flats concrete work completed.                

  2. Fifth floor to sixth floor column concrete work under progress.                

  3. Block work in Second and Third floor under progress.                

  4. Excavation in UG Sump and 1B driveway (Podium) area completed. Balance work under progress.                

​

Tower 2A                    

  1. Corridor tiles laying up to 12th floor completed.                

  2. Common and fire fighting Staircase tiling up to 12th floor completed.                

  3. Pent house tiling under progress.               

  4. MS works in internal flats under progress (Window Grills).

  5. Staircase railings completed. Pent houses individual staircase under progress.          

  6. Internal plastering pent houses completed except some touch up works.           

  7. Flats internal Tiles laying upto 10th floor completed. Pent houses under progress.

  8. External primer and colour applying work under progress.                   

 

Tower 2B                    

  1. Corridor tiles laying up to 12th floor completed.                

  2. Common and fire fighting Staircase tiling up to 12th floor completed.                

  3. Pent house tiling under progress.               

  4. MS works in internal flats under progress (Window Grills). Staircase railings under progress. Pent houses individual staircase under progress.                

  5. Internal plastering pent houses completed except some touch up works.    

  6. Flats internal Tiles laying up to 10th floor completed.                 

  7. External plastering 100 % completed.         

  8. External primer and colour applying work under progress.                

10th May 2018

Tower 1 A                    

  1. 9th floor to 10th floor first three flats columns concrete under progress.             

  2. 9th floor balance three flats concrete work completed.                

  3. Block work Fourth and Fifth floor under progress.                

​

Tower 1 B                    

  1. Fourth floor Balance three flats concrete work completed.                

  2. Forth to Fifth floor first three flats columns concrete under progress.     

  3. Block work in Ground and 1st floor under progress.                

  4. Excavation under progress near east side podium area.             

 

Tower 2 A                    

  1. Corridor tiles laying up to 12th floor completed.                

  2. Common and fire fighting staircase tiling up to 12th floor completed.                

  3. Pent house tiling under progress.               

  4. MS works in internal flats under progress (Window Grills). Staircase railings completed. Pent houses individual staircase under progress.          

  5. Internal plastering pent houses completed except some touch up works.   

  6. Flats internal Tiles laying up to 10th floor completed.                 

  7. External primer and colour applying work under progress.                

                    

Tower 2 B                    

  1. Corridor tiles laying up to 12th floor completed.                

  2. Common and fire fighting Staircase tiling up to 12th floor completed.                

  3. Pent house tiling under progress.               

  4. MS works in internal flats under progress (Window Grills). Staircase railings under progress. Pent houses individual staircase under progress.                

  5. Internal plastering pent houses completed except some touch up works.   

  6. Flats internal Tiles laying up to 10th floor completed.                 

  7. External plastering 100 % completed.

  8. External primer and colour applying work under progress.                 

19th April 2018

Block 2A

  1. Corridor tiling under progress in 10th to 5th floor.

  2. Staircase railings under progress from 12th to 5th floor.

  3. External plastering completed.

  4. MS works 7th to pent houses under progress.

  5. Internal plastering of penthouses under progress.

  6. Flats internal Tiling upto 10th floor completed. 

  7. External primer and colour applying work under progress.

​

Block 2B

  1. Corridor tiles laying under progress in 10th to 5th floor.

  2. Staircase railings under progress in 12th to 5th floor.

  3. External plastering 7th to Terrence 75% completed, balance under progress.

  4. Internal plastering lower and upper pent houses under progress.

  5. Flats internal tiles laying up to 10th floor completed. 

  6. External primer applying work under progress.

​

Block 1A 

  1. 8th floor balance three flats concrete completed .

  2. 8th floor 9th floor columns under progress.

  3. Block work Third and Fourth floor under progress.

​

Block 1B

  1. Third floor balance three flats concrete completed.

  2. Third to fourth floor first 3 flats column casting under progress.

  3. Block work in Ground floor started.

  4. Excavation under progress near east side podium area.

8th March 2018

Tower 1 A                    

  1. 8th floor first three flats shuttering and bar bending work cpmpleted, ready to pour concrete.                

  2. 8th floor balance three flats column concrete completed. Shuttering work under progress.       

  3. Third and Fourth floor under progress.                

Tower 1 B                    

  1. Third floor first three flats concrete completed.                

  2. Second floor to third floor balance three flats columns concrete work completed, shuttering work progress.                

  3. Excavation under progress near east side podium area.                

 

Tower 2 A                    

  1. Over Head Tanks concrete works completed.   

  2. Block work in lift opening side walls completed.                

  3. External plastering south under progress.(7th floor to terrace, near south side)      

  4. MS works 7th to pent houses under progress.                

  5. Internal plastering pent houses under progress.                

  6. Tiles laying up to 10th floor completed.                 

Tower 2 B                    

  1. Terrace Lift head room and Staircase head room, OHT concrete work completed.              

  2. Lower pent house and upper pent house block work completed.                

  3. External plastering 7th to Terrace floor under progress.                

  4. Internal plastering lower and upper pent houses under progress.                

  5. Tiles laying work up to  10th floor completed.                

29th February 2018

Block 2A

  1. Over Head Tanks concrete works completed.

  2. Block work completed in lift opening side walls.

  3. External plastering under progress in 7th floor to terrace- south side. Balance plastering completed.

  4. MS works 7th to pent houses under progress.

  5. Internal plastering pent houses under progress.

  6. Tiles laying work completed upto 10th floor.

​

Block 2B

  1. Terrace Lift head room and Staircase head room, OHT concrete work completed.

  2. Block work completed in Lower pent house and upper pent house.

  3. External plastering under progress in 7th to Terrace floor.

  4. Internal plastering under progress in lower and upper pent houses.

  5. Tiles laying work completed upto  10th floor.

​

Block 1A 

  1. 8th floor first three flats shuttering and barbending work completed, ready for concreting.

  2. 8th floor balance three flats column concrete completed. Shuttering work under progress.

  3. Block work under progress in Third and Fourth floor.

​

Block 1B

  1. Third floor first three flats concrete completed.

  2. Second floor to third floor balance three flats columns concrete work completed, shuttering work under progress.

  3. Excavation under progress near east side podium area.

​

External Works (Hardscape):

  1. North side compound (upto building expansion joint) RCC wall and drain wall work progress.

  2. Balance excavation under progress.

29th January 2018

Block 2A

  1. Over Head Tanks concrete works completed.

  2. Block work completed in lift opening side walls.

  3. External plastering under progress in 7th floor to terrace- south side. Balance plastering completed.

  4. MS works 7th to pent houses under progress.

  5. Internal plastering pent houses under progress.

  6. Tiles laying work completed upto 10th floor.

​

Block 2B

  1. Terrace Lift head room and Staircase head room, OHT concrete work completed.

  2. Block work completed in Lower pent house and upper pent house.

  3. External plastering under progress in 7th to Terrace floor.

  4. Internal plastering under progress in lower and upper pent houses.

  5. Tiles laying work completed upto  10th floor.

​

Block 1A 

  1. 8th floor first three flats shuttering and barbending work completed, ready for concreting.

  2. 8th floor balance three flats column concrete completed. Shuttering work under progress.

  3. Block work under progress in Third and Fourth floor.

​

Block 1B

  1. Third floor first three flats concrete completed.

  2. Second floor to third floor balance three flats columns concrete work completed, shuttering work under progress.

  3. Excavation under progress near east side podium area.

​

External Works (Hardscape):​

  1. North side compound (upto building expansion joint) RCC wall and drain wall work progress.

  2. Balance excavation under progress.

4th December 2017

Block 2A

  1. Terrace Lift head room and Staircase head room slabs completed. OHT under progress.

  2. Block work upper pent house and parapet walls under progress.

  3. External plastering north and west side,  7th to terrace - 50% completed. Balance under progress.

  4. MS works 7th to 10th floor under progress.

  5. Internal plastering 10 th floor under progress.

  6. Tiles laying upto 10th floor completed except some sold flats. 

​

Block 2B

  1. Terrace Lift head room and Staircase head room, OHT under progress.

  2. lower pent house and upper pent house block work under progress.

  3. External plastering up to 7th floor completed.

  4. Internal plastering 8th floor completed, 9th and 10th under progress.

  5. Tiles laying work up to 8th floor completed. 9th floor under progress.

​

Block 1A 

  1. Sixth floor first three flats concrete work completed.Balance flats shuttering work under progress.

  2. Sixth floor to seventh floor columns concrete work under progress (first three flats)

  3. Ground and first floor block work under progress.

​

Block 1B

  1. first floor 3 flats slab cocrete completed.

  2. Ground to first floor balance flats column concrete work under progress.

  3. Excavation under progress near east side podium area.

2nd November 2017

Block 2A

  1. Terrace parapet works under progress.

  2. Block work upper pent house under progress.

  3. Internal plastering is completed upto 7th floor and 8th floor is under progress MS works under progress from 3rd to 7th floor.

  4. Tiles laying work completed upto 7th floor.

​

Block 2B

  1. Concrete work completed till upper pent house.

  2. Column concrete work under progress from upper pent house to terrace slab.

  3. Block-work completed till 10th floor. 

  4. External plastering completed till 7th floor.

  5. Internal plastering works under progress in 7th floor.

  6. Tiles laying work completed till 3rd floor and 4th & 5th floor under progress.

​

Block 1A 

  1. Concrete work completed till 4th floor.

  2. Column concrete work under progress from 4th to 6th floor.

  3. Block-work under progress in ground floor’.

​

Block 1B

  1. Concrete work completed in ground floor.

  2. Shuttering work under progress in ground floor.